A variation is an instructed change to the scope, quality or sequence of the works. It should be issued in writing with an agreed price and any time effect before the work is carried out, otherwise disputes over cost follow.
Variations are the main reason self-builds overrun. Each change looks small on its own, but late changes cost more than the same change made at design stage because they disrupt work already done or ordered.
Keep a running variations register showing the instruction, the agreed cost and the revised contract sum, and reconcile it at each stage payment.