SiteRep

How long does planning permission take in Ireland?

A standard planning application takes a statutory minimum of eight weeks for the council to decide, but requests for further information, appeals to An Coimisiún Pleanála, or a large volume of submissions can extend the overall process to several months or longer.

Under the Planning and Development Act 2000, a local authority must make a decision on a valid planning application within eight weeks of receipt, during which time there is a five-week public observation period allowing anyone to make a submission on payment of the prescribed fee. If no further information is sought and no appeal is lodged, most straightforward domestic applications are decided within this eight-week window and become effective four weeks after the decision, once the appeal period has passed without an appeal.

The timeline extends significantly if the council issues a request for further information. The clock stops until you respond, and once you do, the council has a further period to make its decision, meaning an application that receives a further information request can easily take three to six months from submission to grant. Complex sites, environmental impact assessment requirements, or a high volume of third-party observations can add further time.

If a decision is appealed to An Coimisiún Pleanála (formerly An Bord Pleanála), the statutory objective is to determine appeals within eighteen weeks, though in practice more complex or contentious cases regularly take longer than this target. Overall, a simple house extension with no objections might be permitted within two to three months of submission, while a contested or complicated rural house application could take the best part of a year once an appeal is factored in.

What affects how long your application takes

Timing depends heavily on these factors:

  • Whether the application is valid on first submission, avoiding a restart
  • Whether the council issues a request for further information
  • The number and nature of third-party observations received
  • Whether the site requires specialist assessment, such as flood risk or ecology
  • Whether the decision is appealed to An Coimisiún Pleanála
  • The current workload and processing times of the specific local authority
  • Whether the application falls within a designated area requiring extra consultation

Building in a buffer of several months beyond the statutory minimum is realistic for most projects that need permission.

How to avoid delays

The most common cause of delay is an incomplete or poorly prepared application that triggers a request for further information. Using a competent designer, checking the local development plan's requirements in advance, and considering pre-planning consultation with the council all reduce the risk of a stalled application. Once granted, remember that permission normally lasts five years, so delays in construction after the grant also need to be tracked.

Sources

Last reviewed 20 August 2026. General information only — not legal or planning advice.

Related questions